Progress — who is holding each package this month
Open this screen in Saral/projects/subcontractors/progress
The first tab of Site & quality: the month's work on every package as lanes — the Package QS, the Director, Accounts — with done against total, and one row per package showing the step it is on, whose it is and when it is due. A QS or PM reads it to see what is stuck and with whom.
You enter
- Nothing: a step is marked done on the lane that owns it
Saral fills in
- Each lane's done / total for this month's steps across every package
- Per package: the step it is on, whose it is, when it is due, and a bar per chain — green done, amber ready now, red overdue
It produces
- The month's position per package, read by Overview and the team canvas
Who holds each package
Every package owes the same steps each month — the application recorded, assessed, approved, noticed, then the bill matched and paid. Each step belongs to one team, so the bars answer who is holding the work right now. A step is done when its record exists (the application saved, the notice issued, the bill paid), never because somebody ticked it.
Reading the package health
Green is done, amber is ready now — the step before it is done and this one can start — and red is overdue against the package's own dates. Unknown is never shown as done. Open a package from Payments → Applications to act on its month; this page only shows where it stands.
Next screen: /projects/subcontractors/applications