Help centre · Projects
Payment notices
Open this screen in Saral/projects/notices
The one door for every payment notice, certificate and pay-less notice to a package subcontractor. A subcontract month valued on Subcontracts → Applications is issued here; a notice against a posted invoice is drafted here from the ledger and the package's terms. Every figure on the notice is derived; you type only the assessment and, on a pay-less notice, the basis.
You enter
- Which notice — payment notice, certificate or pay-less notice
- A gross valuation to date only where it differs from the pre-fill, and any deductions with a reason each
- On a pay-less notice: the sum previously notified and the basis of calculation (required by s.111(4))
- A notice sent outside Saral — its kind and date — so the month locks without a second notice
Saral fills in
- The invoice list from the ledger — unpaid first — with due date, notice-by, pay-less-by and final date from the package's terms
- The gross valuation pre-filled from the confirmed subcontract month, previously certified from earlier notices, retention at the package rate, VAT at the invoice rate
- The sum previously notified on a pay-less notice, from the earlier payment notice
- The ladder as it will print, and a live PDF preview that rebuilds as you type
It produces
- A numbered, filed PDF on the contracting entity's letterhead — an issued notice cannot be withdrawn
- The draft as PDF and Excel with formulas, never emailed as if it were the notice
- An email of the filed notice through the one send door, logged on Correspondence
Recorded as sent outside Saral
On a subcontract month, 'Record a notice sent outside Saral' takes the kind and the date and locks the month without producing a document. A record like that can be cleared; an issued notice cannot. A month flagged as issued outside Saral on the Applications tab links its original here and is never re-issued.
Contract letters
The second view on this page composes the letters the registers call for — to subcontractors and the client — from the same records. Each register's 'Issue the letter' link lands here with the letter pre-selected.
Where the figures come from
The subcontract month's gross comes from the confirmed valuation on Subcontracts → Applications; the ledger invoice, its net and VAT rate from Xero; the dates from the package's terms on Procurement; retention from the package, the payment schedule or the account default, in that order.
Next screen: /projects/valuation
Not what you needed? Inside Saral, ask Kuku (Alt+K) — if it cannot answer, “Ask a human” sends the question to Saral support with the chat attached.